Home Portfolio Dublin Port Berth 52 and Berth 53

Nov 2024

Dublin Port Berth 52 and Berth 53

As part of Dublin Port's 2040 Master Plan, we led the marine spread coordination and on-site management for heavy tubular piling, successfully utilising a 400-tonne jack-up barge to deliver safe, precise execution at sea.

ClientDublin Port Company
RoleOn-Site Marine Project Management
Duration6 Months
ContractNEC4 Professional Service Contract (PSC)
ExpertiseMarine Engineering, Project/Contract Management

Project Overview

Forming a cornerstone of the Dublin Port 2040 Master Plan, the development of Berths 52 and 53 demanded elite marine engineering oversight. SHEANEY was appointed to manage the complex installation and testing of heavy tubular piles for the new jetty and dolphin structures.

Our Delivery

Led directly on-site by our Managing Director, we managed the entire marine spread sizing and vessel planning, notably utilising the 400-tonne Admiral 1 jack-up barge. We coordinated specialist subcontractors, handled stability analysis and lift planning, and provided vital input into the temporary works and piling gate design.

Key Achievements

  • Seamlessly managed movements and logistics with the Dublin Port Authority in one of the busiest commercial ports in the region.
  • Directed tier-one contractors including Ocean Crest Marine, Gabriel O'Brien Crane Hire, and Lloyds Datum Group.
  • Maintained rigorous, transparent programme management through Smartsheet and Primavera P6 under an NEC4 framework.